|
Performance
& References
- Finn
Inc.'s experience is proven by our past performance. The following are
some examples of Finn Inc.'s quality performance.
HOLCIM
INC.
Weirton Plant, WV
Cold
Runner (Large U-trough) used to transport molten slag that has just
been granulated,

Troughs / Launders |
into
a receiving hopper eventually into the dewatering system. The molten
slag is approximately 1,450°
F when it passes over the Blow Box or water injection system. This very
abrasive slurry impacts the cold runnern at extremely high velocity.
Earlier they used Hardox 400 wear plates in the cold runner. The whole
system now has our Ceramic (1") lining that holds up extremely
well. Hardox steel plates lasted only 3-6 months when our U-Trough sections
has not been replaced since the first was installed in June 2000.
Advanced Ceramic Tiles |
For
the rest of this slurry system almost all Pipes, Bends, Tees, Laterals,
Spools,
Reducers, Spray Bars and the Blow Box have our Ceramic products. Previously
most of these were Basalt Lined products.
Separator
in closed Circuit with Roller Mill for Granulated Slag. The Separator
has a 7ft high and 9ft ID cylindrical part and a 4 ft high (9 ft ID
at top) cone in the lower part. Finn Inc lined the cone on site with
3/4" thick castable Ceramic and for the cylindrical part we prefabbed
curved Tiles with anchors for welding to the steel cylinder frame. This
was done to reduce the down time. Since installation in March 1999,
very little wear is observed as of summer 2004.
HOLCIM INC.
Theodore Plant, AL
Pneumatic transportation of Granulated blast furnace slag.
Velocity 750 ft/min, 80% solid. A total of 20 long pipes and 2 Sweeps,
90°. All Ceramic linings are 1⁄2" thick inside 6"
Sch 40 pipes i.e. 5" ID. Pipes installed in January 1998. All pipes
are still in operation.
HOLCIM INC.
Dundee, MI
Dust Pipe Nozzle, Hood, Backing Plate and Insert for Cement
Kiln.

Long Pipes |
CEMEX
Wampum Plant, PA
Pneumatic transportation of very abrasive Clinker dust.
Finn Inc has delivered 63 long pipes since July 1996. Most are 10.5
ft long with 1⁄2" thick Ceramic linings, 4" ID. All
straight pipes are still in operation. In addition we have delivered
90°,
60°,
30°
lined Sweeps, Pythons and a number of Laterals, Y's, feed pipes and
more for the same clinker system..
CEMEX
Kosmos Cement Plant, PA
Raw Mill Feeder lined with 1 - 2" Ceramite. Includes
Steel Fibers to improve impact resistance due to coarse particles i.e.
Limestone 2" and smaller in a slurry. First Feeder installed March
1995. Previous used small Ceramic tiles that lasted only 1 - 2 weeks.
FINN INC's feeder was still in operation after 7 years when the plant
was closed.
LAUREL ALUMINUM
CASTING CO.
Glassport, PA
Pneumatic transfer of - 60 mesh silica form sand from truck
to top of silo. Ceramic Wear Back on 4" Sweep (90°). Installed
in June 1993. Still in production after more than 3,500 tons has passed
through the sweep. Steel Pipe Sch. 80 lasted 110 tons.

Butterfly Valves |
ORION
POWER MIDWEST
Cheswick Power Plant, PA
Butterfly Valves (Dampers) with Finn Inc. designed valves
and Transition Pieces(Spools) in connection with Coal Pulverizing Mills.
Ceramic linings 3/4" - 1" thick with 19.5" - 20.5"
ID. First pieces installed spring of 1997. A major improvement of previous
parts made of cast iron.
RELIANT ENERGY
Conemaugh Station, PA
A large number (more than 50) of Spools, Reducers and combinations
for slurry exhaust cleaning system: classifier recircle line, feed pump
discharge, reagent feedback etc. Ceramic lining typical 1⁄2"
thick with ID ranges from 1.5" - 7.5". First installed February
1997. Some of these pieces have been a combination of castable ceramic
with "advanced ceramics". Our products replace mostly Ceramic
Tiles (problem with seams).
RELIANT
ENERGY
Seward Station, PA
Sweeps on top of Bag Houses for transport of Fly Ash on Separator
lines. Sweeps are lined with 1⁄2" Ceramic, 2.5" ID.
Pipes installed in May 1995. Still in production when plant was closed.
DAYTON
POWER & LIGHT CO.
Killen Electric Generator Station, OH
Relining of worn out Pump Housing used for pumping fly ash
slurry. Installed 1997 and still in production in 2003. New housing
last 3 - 5 years. Conclusion: Relined with Finn Inc's Ceramic lining
last 20 - 100% longer than original housing and at a price of less than
half of a new housing.

Tee
WB
Sweep |
DUQUESNE
LIGHT
Elrama Power Station, PA
Tees and Spools in scrubber system containing less than
6% Fly Ash for cleaning exhaust gases. Linings
3/4" thick with 14" ID, installed first time in April 1993.
Life time assumed to be about 10 years, when Rubber Linings last 1 -
2 years.
Wear
Back Bend, 45°
S-shaped 6" ID Bend for pneumatic transportation of Fly Ash. WB
2" thick at center. First installed March 1995.
USSTEEL
Edgar Thompson Plant, PA
BOP Gas cleaning Slurry System. All Pipes/Bends/Tees/Grizzly
(1" thick ceramic layer) /Splash Plates with significant wear problems
were changed to Finn Inc.'s products, lined with 3/4" thick castable
Ceramic. One pipe is 18 ft long with 21 3/4" ID. First Bend installed
June 1996. All are still in operation. Original Bends made of Sch.80
last only 6 months. Kinpactor Tiles made of Ceramic tiles were changed
to Finn Inc's Kinpactor Tiles (more than 60 delivered) made in one monolitic
Castable Ceramic piece without seems, cast on stainless steel. First
delivered January 1966.
USSTEEL
Minntac Mine, MN

WB Bends |
Transport
of 3/8" pellets. Finn Inc has delivered a total of 34 WB Bends,
45°,
both 8" and 10" ID with 2" thick WB at center line. First
installed in February 1994. Previous Sch.80 steel Bends lasted only
6 months.
USSTEEL
Irvin Works, PA
Pneumatic transportation of -1/4" Limestone. Sweep
90°
with WB (1.5") installed 1995.Ceramite coated pipe with 45°
WB Bend.
OHIO
EDISON
W.H.Sammis Plant, OH
Fly Ash Vent. Lines. A number of Finn Inc.'s Sweep 45°,
lined with 1⁄2" Ceramic, 1.5" ID. Lines installed in
November 1994.
CINERGY
Zimmer Station, OH
More
than 20 S-Valves, in Fly Ash system, lined withCeramic
Material. Mostly repair butalso
replacement of new ceramic tile linings. The first installed in 1993.
Lifetime 4 - 8 years
compared with 4 - 6 months without lining. Also lined removable WB with
Ceramite together
with WB placed on 30°
Bends (10"ID), 2" thick at center line
Sweep |
CINERGY
East Bend Station, KY
Ventilation Pipes between hoppers and pipes in connection
with pneumatic Fly Ash
transportation. Eight Sweeps 90°
with 3/4" thick Ceramic lining inside 3" Sch.40 pipes, 1.5"ID.
First installed February 1994. We also delivered Fan House and Fan Wheels
lined with Castable Ceramic material.
VIRGINIA POWER
Possum Power Plant, VA
1 Spool (8" ID), 2 Venturies, Lateral (12" ID)
in Ash Sluice System, Reducer (12" - 8"), 90°
Bend (9 3/4" ID - 5/8" Ceramite), Long Pipes - Ash Pipes (8
ft - 5 3/4" ID - 1/2" Ceramite). First installed in 1999.
MIRANT MID - ATLANTIC, LLC.
Potomac River Generating Station, VA
Long Pipes and 90°
Wear Back Bends for Bottom Ash Pneumatic transportation. Average size
of coal conveyed is 1/4" with a maximum size of 1.5". Long
Pipes lined with 5/8" Ceramic with 7 3/4" ID. Longest pipe
13' 3" long. Our Ceramic Wear Backs are placed on top of original
old/new Manganese Steel WB, 8" ID. WB Bends have 2" thick
Ceramic on center line. Lifetime original Bends with manganese WB are
1⁄2 - 1 year. First pipe installed December 1994. Our WB Bends
outlast the Manganese bends 2-4 times and cost less than the original
bends. We have delivered more than 50 WB Bends to Potomac. WB Bends
90°
also used in conveying coal from Mills to burner.
ZINC
CORPORATION OF AMERICA
Monaca, PA
Pneumatic transportation between Bag House Dust Collector
to Transit Bin for return to
production. Material is as ZnO, FeO and Coke, -60 mesh. Straight Pipes
4 3/4" ID , with 5/8"
thick linings. The first of three were installed one in May 1996.
Finn
Inc. also lined "Preheaten Exaust Transition"(Chutes) with
1" thick Ceramite. First of 5 Chutes was in production March 1998.

Ceramic Bearings |
AK STEEL
CORPORATION
Middletown,
OH
Sinter Recycle Plant. A large number of Finn Inc's Ys, Bends
(45°) and Spools have been
installed since the first Y was tested in 1998 in this very abrasive
environment. Linings are 5/8" thick with ID 6 3/4". Still
in production when Sinter Recycle Plant was closed in 2003.
The Ceramic Bearings are used on Stabilizing Pot Rolls that are submerged
in melted Aluminum. Eight Ceramic Bearings, 3.980"ID, were first
tested at the plant in 2004. Additional 24 Ceramic Bearings were delivered
in August 2005.
CAPARO STEEL
Farrel, PA
Pneumatic transport to Lime Silo. A total of 10 WB Sweeps,
90°, 4" ID with 6 ft center radius. First delivered April 1996.
Center thickness of WB is 3".
DAKOTA GASIFICATION
COMPANY
Great Plains Synfuels Plant, ND
Different configuration of Suction Multiple Tees for Ash
slurry. Lined with 1" thick castable Ceramic. Replaced Basalt Tees.
First piece installed April 1999.
AMERICAN
ELECTRIC POWER (AEP)
Mitchell Plant, WV
Spools, Reducers and 90° Bends, all linings (7-7.5"
ID) of existing/worn out parts in the Hydroveyor Line (Slurry System
for Fly Ash). First pipes repaired Fall 1996. Also lined pipes
for Bottom Ash delivered.
STUART M.
PERRY
Berryville, VA
Pneumatic transport of -20 mesh re-ground pelletized limestone.
Wear Backs on 4" Sweeps both 90° and 45°. Center thickness
of Wear Back 2". First delivery September 2000

WB Sweeps |
Ohio Valley El. Corp/Indiana-Kentucky El. Corp, Kyger Creek Station,
Cheshire, OH
Pneumatic conveying line, 90%-325mesh magnetite. Twelve 30deg. and 45deg.
Ceramic WB Sweeps, 5"ID, installed Fall of 2005.
|